  • Hey all, just changed over the backend after 15 years I figured time to give it a bit of an update, its probably gonna be a bit weird for most of you and i am sure there is a few bugs to work out but it should kinda work the same as before... hopefully :)

Another update...

Jannard

Red Leader
Joined
Dec 28, 2006
Messages
8,248
Reaction score
7
Points
0
EPIC-Ms will continue to be made given that the parts and pieces are available. EPIC-M are not full featured... but have most of what you want.

EPIC-X Stage 2 will ship a few before NAB, production will continue after a slight delay due to Japan supply chain issues end of April. All features will not be available for early EPIC-X and upgrades will come as they are enabled.

All orders for Stage 2 and 3 will be shipped before summer's end 2011 (this year).

Order taken for EPIC-X at NAB will be shipped by summer's end.

EPIC-S will beging production as soon as EPIC-X orders are filled.

Hope this helps you with your planning...

Jim
 
Will Epic M be full featured at a later date as firmware and updates are available?
thanks for updates....

Edit: asked for an M, but my serial is rather high at 1200 + any possibility to actually get one? emailed as requested last month, no reply, but assuming that i'm way up the list. thanks...
 
Will Epic M be full featured at a later date as firmware and updates are available?
thanks for updates....

Edit: asked for an M, but my serial is rather high at 1200 + any possibility to actually get one? emailed as requested last month, no reply, but assuming that i'm way up the list. thanks...

Of course EPIC-M will be updated to be full featured. All EPIC-M customers are being considered seriously and will be contacted as they roll out.

Jim
 
Will Epic M be full featured at a later date as firmware and updates are available?
thanks for updates....

Edit: asked for an M, but my serial is rather high at 1200 + any possibility to actually get one? emailed as requested last month, no reply, but assuming that i'm way up the list. thanks...

absolutely, Epic-Ms will share the same firmware as Epic-X when Epic-X starts to roll out.. features are being added weekly.

Email Kelly again so she knows you are on the Epic-M list.

Epic-M will start shipping again later next week as the dust settles on the big move to the new production facility in Irvine .
 
Thanks Jim!! This kind of guestimating Helps a LOT... even if it changes in 2 weeks. :) Communication is greatly appreciated for planning. Thank you again.
 
Order taken for EPIC-X at NAB will be shipped by summer's end.

EPIC-S will beging production as soon as EPIC-X orders are filled.

Hope this helps you with your planning...

Jim

Thanks Jim.

Clarification question #1: does "as soon as EPIC-X orders are filled" mean EPIC-X orders taken at NAB? Presumably people will continue to order EPIC-X cameras throughout this year and into the next...and EPIC-S would start shipping before that no?

Clarification question #2: EPIC-S will begin production as soon as... Does this entail a few months of getting up to speed with the production line, working kinks out of early EPIC-S prototypes, etc. or does it mean EPIC-S cameras will be shipping within something short, like a month, after production begins.

Regards and thanks for the updates.
 
Any news on the Epic-S front?(specs/price) Or are you reserving that for NAB?
 
Not to get bogged down on semantics but what does summer end mean? as up in Canada summer is rather short :)

Is serial 4000 epic stage 3 by mid june realistic (i'll even wear a Taylor Hall jersey as I know you guys like Edmonton)
 
Thanks for the update! This certainly helps with planning - only question is when can we expect locked down specs on EPIC-S? At NAB I assume? Either way, looking forward to the day :beer:
 
Technically summer ends in September... so that means all Stage 2 and 3 should be shipped well before then. All orders placed at NAB will certainly be shipped before then.

Jim
 
Last edited:
EPIC-S specs locked down by NAB.

Jim
 
All orders for Stage 2 and 3 will be shipped before summer's end 2011 (this year).

Order taken for EPIC-X at NAB will be shipped by summer's end.

Jim

Is there a high probability that most EPIC-X stage 2's will be delivered in late September at about the same time as EPIC-X's ordered at NAB?

In other words, for planning purposes, should most EPIC-X stage 2 buyers plan on end-of summer as worst case scenario or most likely scenario?

Thanks,

-michael zaletel
 
Is there a high probability that most EPIC-X stage 2's will be delivered in late August at about the same time as EPIC-X's ordered at NAB?

In other words, for planning purposes, should most EPIC-X stage 2 buyers plan on end-of summer as worst case scenario or most likely scenario?

Thanks,

-michael zaletel

I would look at Stage 2 to be shipped by May/June.

Jim
 
Here goes that one post everyone groans at.

Scarlet 2/3rds fixed, woould components for it begin trickling in, or has nothing been ordered for it?
 
Summer

Summer

In the United States, summer is often fixed as the period from the summer solstice (June 20 or 21, depending on the year) to the fall equinox (September 22 or 23, again depending on the year).
Source : http://en.wikipedia.org/wiki/Summer

So all stage 2 and stage 3 and orders taken at NAB 2011 will be delivered by Sept 2011 end.

I hope I get my Stage 2 (Red 5xxxx) by July end...maybe earlier depending on stage 2 bookings.

Harcharan
 
I would look at Stage 2 to be shipped by May/June.

Jim

Thanks. I know RED is doing everything they can. Considering the challenges faced and unforeseen supply chain issues, June would be most generous. Even July would be understandable. May would be an early Christmas.

-michael zaletel
 
In the United States, summer is often fixed as the period from the summer solstice (June 20 or 21, depending on the year) to the fall equinox (September 22 or 23, again depending on the year).
Source : http://en.wikipedia.org/wiki/Summer

So all stage 2 and stage 3 and orders taken at NAB 2011 will be delivered by Sept 2011 end.

I hope I get my Stage 2 (Red 5xxxx) by July end...maybe earlier depending on stage 2 bookings.

Harcharan

Expect Stage 2 to be completed by June. Stage 3 to be completed by July/August. All orders at NAB to be completed by September.

Scarlet fixed updates at NAB.

Jim
 