Lawrence Steele
Active member
Not only covid to blame..
Brandon Fowler - May 23 2019 at 11:46 PM
We just sent the 841st Solaris Controller out today. It won't be long before only a handful are left. As stressful as this has been it's a great feeling. A lot of people never thought they would ever ship. It won't be much longer before we are all caught up on your pre-order mats and power units, too.
Now some good news! I've got some more standard daylight mats in the warehouse ready to ship. Regine will start reaching out to people tomorrow about them. If you need yours urgently write me ASAP. The next batch will be in approximately 3 weeks. There will be high-power mats in the next batch also. The next batch of power units will be the 3rd or 4th week of June.
The frames are behind schedule because one of the suppliers is moving incredibly slow. The hard part is done and all that is left is this one part which was supposed to be simple. I'm talking with other suppliers now but still hoping the original one comes through soon. Either way, we are 90% done.
Next week I'm meeting with the manufacturer of the lightboxes in person to finalize the design. It's all locked except for the bag, which was a last minute addition that greatly complicated things. I thought it would be cool to have a bag that can hold the entire kit, frame, lights and all, and that ended up increasing the shipping costs by too much, especially for international shipments. They have been working on some revisions for the bag that will bring the shipping costs down. We are also going to be discussing other options to help bring shipping costs down.
The RGBA strips are booked to start production on Monday and will be ready in 2 weeks.