OK... so listen up.
You/we want it all.
You/we want it now.
You/we want us to consider new ideas and incorporate them in the program to make the project better... as SOON as we can. The market is changing and so must we.
But you/we don't want any schedule slips...
Even with the softening of our urgency (no more 20 hour work days) and all the changes we have made and are making, we are still hoping for late summer of this year to begin the rollout of the new lineup. We have only one wild-card that could irritate all of us... the ASIC. But we are taking every precaution we can to not have that bite us.
But please remember that more features and keeping the schedule are mutually exclusive. At some point, you/we have to pick one or the other. After this latest round of changes... we are done. If you want more... there is a price to pay in the schedule.
Jim
You/we want it all.
You/we want it now.
You/we want us to consider new ideas and incorporate them in the program to make the project better... as SOON as we can. The market is changing and so must we.
But you/we don't want any schedule slips...
Even with the softening of our urgency (no more 20 hour work days) and all the changes we have made and are making, we are still hoping for late summer of this year to begin the rollout of the new lineup. We have only one wild-card that could irritate all of us... the ASIC. But we are taking every precaution we can to not have that bite us.
But please remember that more features and keeping the schedule are mutually exclusive. At some point, you/we have to pick one or the other. After this latest round of changes... we are done. If you want more... there is a price to pay in the schedule.
Jim